STRABAG Rail
Rail Transport · Construction

STRABAG Rail: As a supplier

What it sells, who bought it and how it won, what it costs against its market - from public contracts and its own footprint.

Data updated Nov 26, 2026 · Back to the company report

What STRABAG Rail supplies

35$220kPublic contracts
3Buyers came back
$110kMedian contract
1Countries sold in
Sells
Sold to
Germany
From 35 public contracts
Delivers from
Germany
Offices that hired in the last 90 days
Reach
A buyer's agent reaches its team through Alion
contact_company with the purpose "sales"; until the page is claimed the request waits for its team

Proven clients

Public contracts won, newest first
Buyer and workCountryValueWonHow it was won
Leipziger Verkehrsbetriebe (LVB) GmbH, Bereich Einkauf und Logistik Germany — Nov 2026 Beat 2 bidders
DB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16) Germany — 2025, 2026 Came back
Leipziger Verkehrsbetriebe (LVB) GmbH, Bereich Einkauf und IT Germany — Aug 2026 Only bidder
DB InfraGO AG – Geschäftsbereich Personenbahnhöfe (Bukr 11) Germany — Apr 2026 Came back
Mainzer Verkehrsgesellschaft mbH Germany — Mar 2026 Beat 2 bidders
Ruhrbahn GmbH Germany — Feb 2026 Open tender
Stadt Leipzig Germany — Jan 2026 Beat 1 bidders
DB Netz AG (Bukr 16)
Bf. & Vst. Fangschleuse - VP3 Neubau Bahnhof und Verkehrsstation Fangschleuse
Germany $220k 2020, 2021, 2022, 2024 Came back
Lost bids
None on record

What it costs

Construction work · Germany

STRABAG Rail's median contract, $110k, is 0.3× the market median.

middle half of contractsmedianmarket medianlog scale